Blackberry Creek Bridge & Dam Construction
Removal of Blackberry Creek Dam
Construction of Blackberry Dam Removal
4 Phases for Implementation
Phase 1 – IDNR and YBSD Forces
Phase 2 – City of Yorkville Contractor
Phase 3 & 4 – IDNR Contractor
Phase 1 – OWR Maintenance Crew (Spring 2012)
- Notch the Dam
- Clear Construction / Maintenance Access
- Build Wetland Preservation Berm around Wetland Area
- Expand Park Pond
- Excavate and stabilize Wetland Preservation Channel
Phase 2 – City of Yorkville Contractor (Winter 2013)
- Install Outlet Structure and pipe
Phase 3 – OWR Contractor (Winter 2012-2013)
- Build Temporary Diversion Through Park Pond
- Install Coffer Dams
- Remove Sediment and Stabilize Channel Between Riffle #2 and Riffle #3
- Remove Coffer Dam upstream of Riffle #3 (water into new wetland bypass)
- Remove Diversion through Park Pond
Phase 4 – OWR Contractor (Winter / Spring 2013)
- Remove Sediment and Stabilize Channel Between Riffle #2 and Dam
- Build Riffle #1
- Complete Dam Removal Per Plans
- Remove Coffer Dam Downstream of Riffle #2
- Build up Construction / Maintenance Access Road around small pond to an elevation of 587.0
- Remove or Backfill Outlet Structure and Pipe