Blackberry Creek Bridge & Dam Construction

 

Removal of Blackberry Creek Dam

 

creek-removal-large

View Larger Map

Construction of Blackberry Dam Removal

4 Phases for Implementation

Phase 1 – IDNR and YBSD Forces
Phase 2 – City of Yorkville Contractor
Phase 3 & 4 – IDNR Contractor

Phase 1 – OWR Maintenance Crew (Spring 2012)

  • Notch the Dam
  • Clear Construction / Maintenance Access
  • Build Wetland Preservation Berm around Wetland Area
  • Expand Park Pond
  • Excavate and stabilize Wetland Preservation Channel

Phase 2 – City of Yorkville Contractor (Winter 2013)

  • Install Outlet Structure and pipe

Phase 3 – OWR Contractor (Winter 2012-2013)

  • Build Temporary Diversion Through Park Pond
  • Install Coffer Dams
  • Remove Sediment and Stabilize Channel Between Riffle #2 and Riffle #3
  • Remove Coffer Dam upstream of Riffle #3 (water into new wetland bypass)
  • Remove Diversion through Park Pond

Phase 4 – OWR Contractor (Winter / Spring 2013)

  • Remove Sediment and Stabilize Channel Between Riffle #2 and Dam
  • Build Riffle #1
  • Complete Dam Removal Per Plans
  • Remove Coffer Dam Downstream of Riffle #2
  • Build up Construction / Maintenance Access Road around small pond to an elevation of 587.0
  • Remove or Backfill Outlet Structure and Pipe